SYRACUSE, NY – TTM Technologies reports significant construction progress at its upcoming ultra-HDI PCB manufacturing facility in Syracuse, as the company enters a critical summer build phase. Site curbing is underway, with paving having commenced in June. Transformers are now set and scheduled for energization in the coming weeks, while final glazing and exterior finishes are on track for July completion.
Interior progress includes:
TTM’s technical team will arrive onsite this summer to begin equipment installation and system integration, initiating the transition from construction to early operations. The Syracuse facility will expand TTM’s advanced manufacturing capabilities and reinforce its position in the ultra-HDI and high-reliability PCB segment.